Major Deliverables
Requirement Specification Document
- Revision of Requirements Document was completed and prototypes were added.
Initial Architecture Document template was created and work is being done on it.
Major Accomplishments
Team completed second revision of RS with Software Requirements and prototypes added. Team also started to work on Architecture document and updated the schedule. Finally team talked about presentation and what should be used in presentation.
Concerns/Risks
What to expect for our presentation.